Pipework Freezing by IDWe Ltd
Client – The Austin Company
Site – Pfizer
Site Location – Sandwich, Kent, CT13
Contract Duration – Across just 3 working days, carried out during normal working hours
Assignment –
We were asked to carry out numerous pipework freezes to pipework as large as 100mm. Plus, supply & fit flanges and valves/plugs.
Highlights of Pipe Freezing Services Completed Included –
Prior to carrying out any work, we attended the site to remove pipework lagging, verify pipework sizes and prepare RAMS in advance.
Pipework freezes were carried out across four locations at Pfizer’s offices in Kent.
Our team started out by freezing two 100mm pipes and two 50mm pipes. Once the pipework freezes had taken hold, we then cut each pipework back, we then welded on the flanges, then supplied and installed the valves/plugs.
In another location within Pfizer, we carried out two pipework freezes, once the pipework freezes had taken hold, we then cut the pipework back and threaded the pipework insitu. Next, we then supplied and installed two 50mm valves/plugs.
Several other pipe freezes were carried out including CHW & LTHW pipework.
A total of 25 pipe freezes were carried out.
The site was cleared of all redundant items upon completion of work and disposed of at a licensed refuse/recycling facility.
Result:
All pipe freezes were carried out successfully.
Everything was left in good working order.
All work took place out of hours with no disruption to services.
~
For further details on IDWe Ltd’s Pipe Freezing Services and to get a quote, please click here.
Get a quote, please call 020 8302 7644 or email: info@idwe.co.uk
Discover all of the services we offer, please click here.
Want to keep up to date with IDWe Ltd’s news & projects? Follow us on social media: Facebook, Twitter & LinkedIn.